Success in SAP Project System with SAP ERP 6.0 EHP4 C_TPLM22_64 exam with the all-inclusive SAP C_TPLM22_64 exam dumps preparation material is offered with money back guarantee so either you embrace the success or get your money back because your success is the central focus. C_TPLM22_64 exam practice test software is designed in a way that it gives you a chance of getting a clear picture of whole syllabus, exam pattern, practice of exam in simulated real exam scenarios and more than all evaluation of your learning independently with self-assessment feature.

♥ VALID C_TPLM22_64 Exam Questions 2018 ♥

C_TPLM22_64 exam questions, C_TPLM22_64 PDF dumps; C_TPLM22_64 exam dumps:: https://www.dumpsschool.com/C_TPLM22_64-exam-dumps.html (100 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest and Most Accurate SAP C_TPLM22_64 Dumps Exam Questions and Answers:

Version: 5.0
Question: 21

Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?
Please choose the correct answer.
Response:

A. Internally-processed activities
B. Externally-processed activities
C. Service activities
D. Scheduled activities

Answer: C

Question: 22

Can you specify in the application which status profile should be used the first time you set a user status where a status profile has not yet been defined in the project profile?
Please choose the correct answer.
Response:

A. Yes
B. No
C. Yes using operative status
D. Yes using status modes

Answer: A

Question: 23

What are the components on which reporting is based upon, in profit center accounting?
There are 2 correct answers to this question.
Response:

A. Cost centers
B. Cost elements
C. Profit centers
D. Profit center hierarchy

Answer: CD

Question: 24

Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other direction?
Please choose the correct answer.
Response:

A. Contractual management
B. Claim management
C. Claim Planning
D. Variance management

Answer: B

Question: 25

Which of the following specifies how much time must elapse between individual archiving steps in network type?
Please choose the correct answer.
Response:

A. Functional areas
B. Residence times
C. Classification indicator
D. Functional areas

Answer: B

Question: 26

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?
There are 2 correct answers to this question.
Response:

A. Billing element
B. Cost element
C. Pricing element
D. Account assignment element

Answer: AD